News & Events

Expansion Update – Week of May 22nd

There will be work this Saturday, May 20th. The 2nd floor slab was finished and the exterior structural stud walls of the 2nd floor were installed this week. Hambro floor joists for the 3rd floor will begin this week and continue through next week. Mechanical rough in work continues on…

Read more…

FREE Summer Concert Series

Read more…

Guest Bartender Night

Read more…

The Conversation Project

Read more…

A Difficult Conversation Made Easier

by Diane Kauffman, Marketing & Sales Manager  The Hickman provides permanent and respite personal care to seniors. You are invited to The Hickman on Wednesday, May 24 at 5:30 p.m. to learn more about The Conversation Project. One of the most difficult and most important conversations I have ever had…

Read more…

Expansion Update – Week of May 15th

For the duration of the project it should be assumed that there will be a few workers on site every Saturday.  Depending on the weather and other factors, there could be up to 20 or 30 workers on site on a Saturday. Second floor joist and deck continue to be set…

Read more…

Expansion Update – Week of May 8th

Waterproofing touch up around the building foundation was done this week. Structural steel stud walls on the 1st floor are complete. Hambro floor joist installation on the 2nd floor will be completed next week.  The 2nd floor will be poured next week and structural steel stud wall installation will begin….

Read more…

Meet the Artist Opening Reception

Read more…

Benefiting from Volunteer Opportunities

by Charles “Ebbie” Alfree III, Director of Advancement Some consider volunteers to be the very backbone of non-profit organizations. When you think about it, the individuals who serve on non-profits’ Board of Directors are volunteers! However, not everyone who offers their time to an organization serves at that capacity; there…

Read more…

Expansion Update – Week of May 1st

Structural steel stud walls for the first floor were set this week. The 2nd floor joists are being installed and prepped for pouring the second floor concrete in the next week. Backfilling around the building continues.   Interior ground floor wall framing will begin next week. No Saturday work is…

Read more…

Grieving our Losses

by Pamela Leland, Phd, Executive Director  Loss is not all of life, but it is a part of life. Amidst the joys and gifts is also loss. Loss of jobs … of friendships … of marriages … of loved ones … loss of hopes and dreams. As we age, the…

Read more…

Expansion Update – Week of April 17th

Steel work is complete. Floor joists are being set.  This will continue for the next month. Structural steel stud walls for the 1st floor will be delivered and started next week. Pouring of concrete floors will begin in the next few weeks.  

Read more…

Expansion Update – Week of April 10th

Contractor will be working this Saturday, April 10th.  Steel work continues and should be completed this weekend. Floor joists arrived this week for installation to start next week. The last section of the ground floor slab on grade was poured this week. The tunnel roof was poured this week. 

Read more…

What Do I Do With All This Stuff?

By Diane Kauffman, Marketing & Sales Manager  As we grow more mature, we begin to need less stuff. I have noticed this about myself. Having moved several years ago, I had already begun to downsize –  reducing the number of belongings filling my closets and drawers. Now, as I am…

Read more…

Expansion Update – Week of April 3rd

Due to the rain today, masons will most likely work on Saturday, April 1st. Foundation work will be 100% complete as of this week. The tunnel roof will be poured next week. Structural steel started this week and will be completed next week. Masonry foundation work will continue next week. 

Read more…