• Paving was completed on the small Walnut Street lot last week. This week the existing Marshall Street parking lot was cleared and only base-paved.  It will be line striped in the next week with the intent of the permanent finished paving to be done in early Spring.
  • The rear memory garden area sidewalk and patio is being poured this week.
  • There is some front and rear patio finish work on ceilings and railings that will be completed over the next two weeks.
  • Inside the building the contractors are removing and clearing out their large tool boxes to make room for the last of the finishes.
  • At this point, most of the finishes in the building have been installed. The contractors only have a few weeks left to complete the last of the flooring, painting, caulking, light fixtures, ceiling tiles, doors and hardware, trim, handrails, etc.
  • All of the mechanical, electrical, plumbing, and fire protection systems have been installed and are now being tested.  All of the testing should be completed over the next few weeks.
  • In early January, the architect will begin going through the building and putting together a punch-list for the contractors to complete.
  • Based on the current schedule, the goal remains to have the building completed in January so furniture and any final punch-list touch up work can be completed in February.

 

I’m always recommending The Hickman. As long-time residents in the area, this is our community. Living here has given my Dad a sense of belonging... a feeling of home.”

The staff here really do care. I enjoy the social aspects, and the food is excellent.”

Within the first week, my Dad settled in. Not long after that, he said one day 'I'm glad it was my idea to come here.”

Call today (484) 760-6300
Schedule A Tour