• The front of the building’s exterior facing Walnut St. is 95% complete.  With the exception of some painting on the siding.
  • Exterior brickwork will be completed next week around the entire building.
  • Exterior wall siding continues around the South and West sides of the building for the next few weeks.
  • Site work and grading on the front of the building will begin next week.
  • On the Marshall Street side of the building the transformer vault will be set next week.
  • Interior drywall work continues.
  • Interior finished trim work continues.
  • Basement painting started this week and will continue as drywall gets finished.
  • The main electrical switchgear was set this week.
  • Elevator installation continues.

Iā€™m always recommending The Hickman. As long-time residents in the area, this is our community. Living here has given my Dad a sense of belonging... a feeling of home.ā€

The staff here really do care. I enjoy the social aspects, and the food is excellent.ā€

Within the first week, my Dad settled in. Not long after that, he said one day 'I'm glad it was my idea to come here.ā€

Call today (484) 760-6300
Schedule A Tour