Expansion Update – Week of September 25th

On: September 23, 2017

  • The front of the building’s exterior facing Walnut St. is 95% complete.  With the exception of some painting on the siding.
  • Exterior brickwork will be completed next week around the entire building.
  • Exterior wall siding continues around the South and West sides of the building for the next few weeks.
  • Site work and grading on the front of the building will begin next week.
  • On the Marshall Street side of the building the transformer vault will be set next week.
  • Interior drywall work continues.
  • Interior finished trim work continues.
  • Basement painting started this week and will continue as drywall gets finished.
  • The main electrical switchgear was set this week.
  • Elevator installation continues.