Expansion Update – Week of September 11th

On: September 8, 2017

  • Exterior siding work continues.
  • The bulk of the brickwork is done that extends up near the top of the building.  The low brick will continue for the next few weeks.
  • Exterior site work will continue around the building for rain leaders.  The water, gas, and electrical underground work are approximately 90% complete.
  • On the interior of the building there are numerous trades working on all three floors. Drywall is approximately 50% complete and most of the electrical and plumbing wall rough in is complete. 
  • Interior trim work will begin this week.
  • Casework will begin over the next few weeks.
  • Workers will be on site this Saturday, September 9th.