• The exterior brick will be completed this week.
  • Exterior siding continues and should be completed within the next 10 days.
  • Sitework around the building continues, the construction trailer has been removed, and rough grading has started.  Over the next month the bulk of the sitework including sidewalks and finish grading will be completed.
  • Interior drywall work is now 80% complete.
  • Interior wood trim continues on the 3rd floor.
  • Ground floor painting is 80% complete.  Painting the first floor will begin next week.
  • The roof top cooling tower will be set in the next two weeks.
  • Interior HVAC and electrical work continues.

Iā€™m always recommending The Hickman. As long-time residents in the area, this is our community. Living here has given my Dad a sense of belonging... a feeling of home.ā€

The staff here really do care. I enjoy the social aspects, and the food is excellent.ā€

Within the first week, my Dad settled in. Not long after that, he said one day 'I'm glad it was my idea to come here.ā€

Call today (484) 760-6300
Schedule A Tour

Send this to a friend