Expansion Update – Week of October 30th

On: October 27, 2017

  • Exterior siding work is 95% complete.
  • All exterior brick work is complete.
  • Sidewalks are being poured this week and next week.
  • Sitework underground piping and grading continues.
  • Landscaping will begin in approximately one week.
  • The transformer for the building and the new power pole has been set.
  • Interior drywall will be 98% complete over the next week.
  • Painting and flooring continue.
  • Interior casework and trim continues.
  • Light fixture installation has started.
  • The large cooling tower on the roof has been set and is being piped in.
  • The second elevator installation continues and will be completed within the next few weeks.
  • Workers will be on site tomorrow 10/28 all day.