Expansion Update – Week of October 23rd

On: October 20, 2017

  • Exterior site grading continues including prepping to pour sidewalks as well as the entrance driveway.
  • Transformer is being set today.
  • Exterior siding continues and should be completed in about a week.
  • Interior drywall is about 90% complete and should be finished in about a week.
  • Painting continues.
  • The floor is continuing to be installed on the first floor and installation will begin in the basement.
  • Molding and trim work continues, as well as setting casework.
  • Interior mechanical and electrical rough ins are nearly complete.
  • The building’s permanent power should be turned on within two weeks.
  • Workers will be on site tomorrow 10/21.