Expansion Update – Week of October 16th

On: October 14, 2017

  • Exterior sitework continues around the building for rain leader piping and grading.
  • Exterior siding is approximately 80% complete and will continue for the next week.
  • Brickwork is being finished over the next few days.
  • Interior drywall work is 85% complete and should be finished within two weeks.
  • Paint continues on the first floor.
  • Trim work continues on the first floor and cabinets have started to be set.
  • Interior wall rough in for mechanical and electrical systems is nearly complete.
  • Flooring will begin on the ground floor this week.