Expansion Update – Week of November 6th

On: November 3, 2017

  • Exterior siding work continues on the back side of the building.
  • The generator was installed this past week.
  • Much of the new stamped concrete sidewalks have been poured over the past week.
  • The tunnel continues to be exposed and waterproofed.
  • Interior drywall is nearly complete.
  • Interior plumbing fixtures are being set.
  • Flooring installation continues.
  • Painting and trim work continue.
  • Cabinets are being set.
  • Light fixtures are being installed.
  • The second elevator installation is nearly complete.
  • Workers will be on site this Saturday November 4th.