• There will be work this Saturday, May 20th.
  • The 2nd floor slab was finished and the exterior structural stud walls of the 2nd floor were installed this week.
  • Hambro floor joists for the 3rd floor will begin this week and continue through next week.
  • Mechanical rough in work continues on the ground floor.
  • Ground floor layout and framing will continue on the ground floor.   