Expansion Update – Week of March 6th

On: March 3, 2017

  • Foundation work continues in the basement and first floor.
  • One stair tower is nearly topped out and the second stair tower work should begin next week.
  • Half of the basement floor will be poured this week.
  • The first elevator shaft is complete and the foundation for the second shaft has been poured. Masonry work on this shaft will begin next week.  
  • Electrical and plumbing work continues.
  • Foundations for steel will continue in anticipation of steel arriving later this month.