Expansion Update – Week of March 27th

On: March 24, 2017

  • Masonry work will continue on Saturday, March 25th.
  • The stair towers and elevator shaft masonry walls are complete up to the three story height of the building.
  • The first steel delivery will arrived on site this week.
  • Tunnel walls were installed and the tunnel lid was poured this week.
  • Foundations are 95% complete.