Expansion Update – Week of March 20th

On: March 17, 2017

  • Due to the snow, a few days were lost this week.  Therefore, the contractor will be working Saturday, March 18th.
  • Foundation work continues and will be completed next week.
  • Masonry foundations, stair towers, and elevator towers continue and will be completed next week.
  • The first steel delivery will arrive on site by the end of next week.