Expansion Update – Week of March 13th

On: March 9, 2017

  • Weather permitting, work may continue at 7:30 AM  on Saturday, March 11th.
  • The South elevator and stair tower masonry walls are approximately 70% complete and will be topped out next week.
  • Foundation work continues and should be close to completion by the end of next week.
  • The tunnel walls have been installed and the tunnel lid will be poured next week.
  • The rest of the site will be prepped and cleaned up next week in anticipation of steel arrival by the end of the month.