Expansion Update – Week of June 5th

On: June 2, 2017

  • There will be work this Saturday, June 3rd.
  • The third floor Hambro joists are set and half of the concrete floor will be poured this week. The rest of the third floor will be poured next week.
  • Ground floor mechanical and electrical system rough in continues.  
  • First floor slab on grade is being prepared to be poured in the next two weeks.
  • Third floor exterior structural steel stud walls will be set next week.