  • The third floor walls have all been completed and the roof truss installation has started.
  • All of the major concrete work is complete at this time.
  • Interior mechanical, electrical, and plumbing rough in continues.
  • Wall framing will begin on the first floor in the next week.
  • Truss work will continue over the next week.
  • Roof work will follow the truss installation over the next few weeks.