  • Interior mechanical, electrical, plumbing rough in continues on the ground floor.
  • Fireproofing the ground floor was completed this week.
  • The third floor exterior walls have been installed.
  • Trusses have been delivered and will be installed along with sheathing of the roof.
  • Roof installation will begin next week.
  • The interior slab on grade for the first floor was poured this week.  This was the last large concrete pour for the project.
  • There will be manpower on site working Saturday.