• The third floor concrete deck pouring and structural wall installation will be completed this week.
  • Ground floor spray on fire proofing is being completed this week. 
  • Next week roof truss installation will begin.
  • Interior 1st floor slab on grade will be poured next week.
  • Mechanical piping and electrical rough in work continues.