Expansion Update – Week of January 9th

On: January 7, 2017

  • Over the past week the basement masonry wall installation continued and is approximately 40% complete. This work will continue for another few weeks.
  • Underground plumbing and foundation waterproofing will begin next week. 
  • The newly renovated High Street parking lot at the Friends School was opened this week for school and meetinghouse use. The Marshall Street parking lot at the Friends School is now permanently closed until construction of the new building is complete.