Expansion Update – Week of January 15th

Posted On: January 15, 2018

  • Exterior fencing has been installed, but not yet painted.
  • Stripes were painted on the parking lot.
  • Inside the building, most of the resident rooms have been completed and were reviewed for punchlist items.
  • Common areas on the 2nd and 3rd floors are nearly complete.
  • Flooring will be finished this week throughout the building.
  • Final painting of the building in all of the common areas continues and should be completed next week.
  • 70% of the building has been final cleaned.
  • Final punchlist inspections started last week and will continue through next week.
  • The goal remains to have the building completed by the end of the month with all punchlist being completed in February.
  • Furniture will be installed in early February.