Expansion Update – Week of December 4th

On: December 1, 2017

  • Exterior work continues with grading around the building, prepping the parking lot between the new and existing Hickman building and finishing the new sidewalks.  The rear Marshall Street parking lot is being cleared of construction storage so the paving work can be done over the next few weeks. 
  • The new gutters are being installed and the last of the exterior siding work continues over the next week.
  • Interior finish trade work continues including casework, trim, painting, ceilings, lighting, and flooring.
  • The contractors continue to work toward completion of the building in January.