Expansion Update – Week of December 18th

On: December 15, 2017

  • Paving of the small parking lot between the Hickman Building and the Anna T. Jeanes Building was completed last week.
  • The rear parking lot off Marshall St. will be paved over the next week.
  • Tremendous amount of work is being done every day on the inside of the building: carpet is being installed, ceiling tiles are going in, building systems such as HVAC and fire alarms are being started up and tested, most of the casework has been installed, painting and trim work continues, doors and hardware are being installed, and kitchen prep equipment and appliances were installed this past week.
  • The project is now approximately 90% complete. Over the next month all of the finishes in the building will be completed and punch list work will begin.