Expansion Update – Week of August 7th

On: August 7, 2017

  • Exterior brick work continues on the Marshall St. side of building.
  • All windows are installed, the roof is completed and the building is water-tight secured.
  • Exterior siding work will begin in a few weeks.
  • Interior wall framing and drywall continues.
  • Interior electrical, mechanical, and plumbing rough ins continue.
  • Storm water pipe installation continues through the Friends School grounds.