Expansion Update – Week of August 28th

On: August 24, 2017

  • Brickwork continues across the front of the building on Walnut Street.  
  • Please note one minor clarification to last week’s update: 
  • The brickwork on the East Marshall Street side is not 100% complete as the update stated. There is still some brick work to be done.
  • Interior drywall work continues including taping and spackling.  Some of the ground floor is ready to receive paint.
  • Wall framing on the second floor has started.
  • Sitework for underground utilities continues around the rear side of the building.
  • Interior electrical and mechanical rough in continues.