  • Exterior brick work continues on the front of the building. East Marshall Street side brick is complete.
  • Drywall work continues.
  • Mechanical, electrical, and plumbing rough in throughout the building continues.
  • Interior wall framing is complete on the first and third floors. The second floor wall framing will start this week.
  • Storm water piping work continues through the Friends School and the Marshall Street parking lot.
  • Over the next month all of the underground utility work will be installed.