• Due to the rain today, masons will most likely work on Saturday, April 1st.
  • Foundation work will be 100% complete as of this week.
  • The tunnel roof will be poured next week.
  • Structural steel started this week and will be completed next week.
  • Masonry foundation work will continue next week. 