Category Archives: Sharpless-Hall Project

Expansion Update – Week of October 16th

Exterior sitework continues around the building for rain leader piping and grading. Exterior siding is approximately 80% complete and will continue for the next week. Brickwork is being finished over the next few days. Interior drywall work is 85% complete and should be finished within two weeks. Paint continues on…

Read more…

Expansion Update – Week of October 9th

The exterior brick will be completed this week. Exterior siding continues and should be completed within the next 10 days. Sitework around the building continues, the construction trailer has been removed, and rough grading has started.  Over the next month the bulk of the sitework including sidewalks and finish grading…

Read more…

Expansion Update – Week of October 2nd

Brick work on the exterior of the building continues and should be completed next week. Exterior siding work will continue on the rear side of the building for the next few weeks. Site work around the building including rain leader piping and grading will begin. Interior drywall work continues including…

Read more…

Expansion Update – Week of September 25th

The front of the building’s exterior facing Walnut St. is 95% complete.  With the exception of some painting on the siding. Exterior brickwork will be completed next week around the entire building. Exterior wall siding continues around the South and West sides of the building for the next few weeks….

Read more…

Expansion Update – Week of September 18th

Exterior masonry work is approximately 80% complete.  Most of the work should be completed over the next few weeks. Exterior cement board siding work will continue. Most of the site underground utilities have been installed.  Over the next month the grading around the building will be roughed in. Inside the…

Read more…

Expansion Update – Week of September 11th

Exterior siding work continues. The bulk of the brickwork is done that extends up near the top of the building.  The low brick will continue for the next few weeks. Exterior site work will continue around the building for rain leaders.  The water, gas, and electrical underground work are approximately…

Read more…

Expansion Update – Week of September 4th

Interior drywall work continues. Mechanical, electrical and plumbing rough in continues. Interior wall framing continues and will be complete within the next few weeks. Exterior brick and siding work continues. Underground exterior utility work continues and is nearly complete.  

Read more…

Expansion Update – Week of August 28th

Brickwork continues across the front of the building on Walnut Street.   Please note one minor clarification to last week’s update:  The brickwork on the East Marshall Street side is not 100% complete as the update stated. There is still some brick work to be done. Interior drywall work continues…

Read more…

Expansion Update – Week of August 21st

Exterior brick work continues on the front of the building. East Marshall Street side brick is complete. Drywall work continues. Mechanical, electrical, and plumbing rough in throughout the building continues. Interior wall framing is complete on the first and third floors. The second floor wall framing will start this week….

Read more…

Expansion Update – Week of August 14th

Exterior brick work continues and most of the Marshall St. side of building is complete. Underground storm water work continues through the Friends School.  This work will continue through next week.   Transformer vault was set.  Waiting for PECO to set the transformer.   Interior wall rough in of electrical…

Read more…

Expansion Update – Week of August 7th

Exterior brick work continues on the Marshall St. side of building. All windows are installed, the roof is completed and the building is water-tight secured. Exterior siding work will begin in a few weeks. Interior wall framing and drywall continues. Interior electrical, mechanical, and plumbing rough ins continue. Storm water…

Read more…

Expansion Update – Week of July 31st

Interior wall framing work continues. Drywall work continues on ceilings and walls. Window installation is complete. Roof work is 95% complete. Interior mechanical piping and electrical rough in continues. Exterior underground storm piping will start up again next week. Exterior brick work continues. Workers will be on site Saturday, July…

Read more…

Expansion Update – Week of July 17th

Interior mechanical, plumbing, and electrical rough in continues. The roof truss work is nearly complete. Exterior wall vapor barrier installation has started.  Window installation is starting this week and will continue through next week.   Exterior wall finished brick work will begin next week. Contractors will be on site this…

Read more…

Expansion Update – Week of July 10th

Interior mechanical, plumbing, and electrical rough in continues. The roof truss work is nearly complete and will be finished next week. Roofing has been installed on about half of the building and will be completely done over the next two weeks. Exterior wall work will continue, which includes starting the…

Read more…

Expansion Update – Week of July 3rd

Most of the roof trusses have been set to date. Roofing is approximately 30% complete and will continue over the next few weeks. Sheathing of the roof trusses will continue next week. Underground piping work on Biddle Street was done this week and will continue through the Friends School. Interior…

Read more…