Category Archives: Sharpless-Hall Project

Expansion Update – Week of December 18th

Paving of the small parking lot between the Hickman Building and the Anna T. Jeanes Building was completed last week. The rear parking lot off Marshall St. will be paved over the next week. Tremendous amount of work is being done every day on the inside of the building: carpet…

Read more…

Expansion Update – Week of December 11th

Exterior work on the building continues including landscaping, sod, paver at the entrance drive. Over the next few weeks the rest of the site will be stabilized for the Winter. The balance of the landscaping and grass will be completed in the Spring.  Paving of the two parking lots started…

Read more…

Expansion Update – Week of December 4th

Exterior work continues with grading around the building, prepping the parking lot between the new and existing Hickman building and finishing the new sidewalks.  The rear Marshall Street parking lot is being cleared of construction storage so the paving work can be done over the next few weeks.  The new…

Read more…

Expansion Update – Week of November 20th

The exterior of the building fa├žade is nearly complete as the painters are finishing the red trim. Sitework continues with the grading of the side parking lot by The Hickman Building.  Landscaping along Marshall St. was supposed to begin last week, but it will start next week. All of the…

Read more…

Expansion Update – Monthly Review

Over the past month tremendous progress has been made on the project.  As you can see the bulk of the exterior of the building has been completed, the site is being graded, the entrance driveway has been paved, the large cooling tower was set on the roof, and a lot…

Read more…

Anna T. Jeanes Building Hard Hat Tours

Read more…

Expansion Update – Week of November 6th

Exterior siding work continues on the back side of the building. The generator was installed this past week. Much of the new stamped concrete sidewalks have been poured over the past week. The tunnel continues to be exposed and waterproofed. Interior drywall is nearly complete. Interior plumbing fixtures are being…

Read more…

Expansion Update – Week of October 30th

Exterior siding work is 95% complete. All exterior brick work is complete. Sidewalks are being poured this week and next week. Sitework underground piping and grading continues. Landscaping will begin in approximately one week. The transformer for the building and the new power pole has been set. Interior drywall will…

Read more…

Expansion Update – Week of October 23rd

Exterior site grading continues including prepping to pour sidewalks as well as the entrance driveway. Transformer is being set today. Exterior siding continues and should be completed in about a week. Interior drywall is about 90% complete and should be finished in about a week. Painting continues. The floor is…

Read more…

Expansion Update – Week of October 16th

Exterior sitework continues around the building for rain leader piping and grading. Exterior siding is approximately 80% complete and will continue for the next week. Brickwork is being finished over the next few days. Interior drywall work is 85% complete and should be finished within two weeks. Paint continues on…

Read more…

Expansion Update – Week of October 9th

The exterior brick will be completed this week. Exterior siding continues and should be completed within the next 10 days. Sitework around the building continues, the construction trailer has been removed, and rough grading has started.  Over the next month the bulk of the sitework including sidewalks and finish grading…

Read more…

Expansion Update – Week of October 2nd

Brick work on the exterior of the building continues and should be completed next week. Exterior siding work will continue on the rear side of the building for the next few weeks. Site work around the building including rain leader piping and grading will begin. Interior drywall work continues including…

Read more…

Expansion Update – Week of September 25th

The front of the building’s exterior facing Walnut St. is 95% complete.  With the exception of some painting on the siding. Exterior brickwork will be completed next week around the entire building. Exterior wall siding continues around the South and West sides of the building for the next few weeks….

Read more…

Expansion Update – Week of September 18th

Exterior masonry work is approximately 80% complete.  Most of the work should be completed over the next few weeks. Exterior cement board siding work will continue. Most of the site underground utilities have been installed.  Over the next month the grading around the building will be roughed in. Inside the…

Read more…

Expansion Update – Week of September 11th

Exterior siding work continues. The bulk of the brickwork is done that extends up near the top of the building.  The low brick will continue for the next few weeks. Exterior site work will continue around the building for rain leaders.  The water, gas, and electrical underground work are approximately…

Read more…