Category Archives: Sharpless-Hall Project

Expansion Update – Week of June 26th

The third floor walls have all been completed and the roof truss installation has started. All of the major concrete work is complete at this time. Interior mechanical, electrical, and plumbing rough in continues. Wall framing will begin on the first floor in the next week. Truss work will continue…

Read more…

Expansion Update – Week of June 19th

Interior mechanical, electrical, plumbing rough in continues on the ground floor. Fireproofing the ground floor was completed this week. The third floor exterior walls have been installed. Trusses have been delivered and will be installed along with sheathing of the roof. Roof installation will begin next week. The interior slab…

Read more…

Expansion Update – Week of June 12th

The third floor concrete deck pouring and structural wall installation will be completed this week. Ground floor spray on fire proofing is being completed this week.  Next week roof truss installation will begin. Interior 1st floor slab on grade will be poured next week. Mechanical piping and electrical rough in…

Read more…

Expansion Update – Week of June 5th

There will be work this Saturday, June 3rd. The third floor Hambro joists are set and half of the concrete floor will be poured this week. The rest of the third floor will be poured next week. Ground floor mechanical and electrical system rough in continues.   First floor slab…

Read more…

Expansion Update – Week of May 22nd

There will be work this Saturday, May 20th. The 2nd floor slab was finished and the exterior structural stud walls of the 2nd floor were installed this week. Hambro floor joists for the 3rd floor will begin this week and continue through next week. Mechanical rough in work continues on…

Read more…

Expansion Update – Week of May 15th

For the duration of the project it should be assumed that there will be a few workers on site every Saturday.  Depending on the weather and other factors, there could be up to 20 or 30 workers on site on a Saturday. Second floor joist and deck continue to be set…

Read more…

Expansion Update – Week of May 8th

Waterproofing touch up around the building foundation was done this week. Structural steel stud walls on the 1st floor are complete. Hambro floor joist installation on the 2nd floor will be completed next week.  The 2nd floor will be poured next week and structural steel stud wall installation will begin….

Read more…

Expansion Update – Week of May 1st

Structural steel stud walls for the first floor were set this week. The 2nd floor joists are being installed and prepped for pouring the second floor concrete in the next week. Backfilling around the building continues.   Interior ground floor wall framing will begin next week. No Saturday work is…

Read more…

Expansion Update – Week of April 17th

Steel work is complete. Floor joists are being set.  This will continue for the next month. Structural steel stud walls for the 1st floor will be delivered and started next week. Pouring of concrete floors will begin in the next few weeks.  

Read more…

Expansion Update – Week of April 10th

Contractor will be working this Saturday, April 10th.  Steel work continues and should be completed this weekend. Floor joists arrived this week for installation to start next week. The last section of the ground floor slab on grade was poured this week. The tunnel roof was poured this week. 

Read more…

Expansion Update – Week of April 3rd

Due to the rain today, masons will most likely work on Saturday, April 1st. Foundation work will be 100% complete as of this week. The tunnel roof will be poured next week. Structural steel started this week and will be completed next week. Masonry foundation work will continue next week. 

Read more…

Expansion Update – Week of March 27th

Masonry work will continue on Saturday, March 25th. The stair towers and elevator shaft masonry walls are complete up to the three story height of the building. The first steel delivery will arrived on site this week. Tunnel walls were installed and the tunnel lid was poured this week. Foundations…

Read more…

Expansion Update – Week of March 20th

Due to the snow, a few days were lost this week.  Therefore, the contractor will be working Saturday, March 18th. Foundation work continues and will be completed next week. Masonry foundations, stair towers, and elevator towers continue and will be completed next week. The first steel delivery will arrive on…

Read more…

Expansion Update – Week of March 13th

Weather permitting, work may continue at 7:30 AM  on Saturday, March 11th. The South elevator and stair tower masonry walls are approximately 70% complete and will be topped out next week. Foundation work continues and should be close to completion by the end of next week. The tunnel walls have…

Read more…

Expansion Update – Week of March 6th

Foundation work continues in the basement and first floor. One stair tower is nearly topped out and the second stair tower work should begin next week. Half of the basement floor will be poured this week. The first elevator shaft is complete and the foundation for the second shaft has…

Read more…